INSTALLATION CONTENTS PAGE 2
3 4 LASTPAGE
1. After
removing machinery from crate, check for damage.
2.
CAUTION needs to be taken when moving or picking up machine. Bowls
are
held to table only by rubber feet. Pick up underneath the base or table,
if
included. The table should not be tipped at a steep angle.
3. When machine is at final location, make sure everything is level.
4. Make
sure mounting surfaces and/or tables are strong and stable enough
to
accommodate machinery. If the mounting
surface vibrates excessively,
it
can cause interference with the vibration of the bowl.
5. Check all bolts and tighten, if required.
6. Make
sure nothing touches bowl, base unit, inline or hopper.
7. Make sure machine is properly grounded
and connected to correct
voltage.
8. DO
NOT OVERLOAD BOWL. Part level should
not exceed height of first
turn
of track inside bowl.
9. Turn machine on and adjust proper speed, generally about 10% more rate
than needed. Time with stopwatch and take average over five (5) minutes.
10. If